Delay Risk Factors in Foundation Works Using SEM and Multi-Group Analysis

Authors

  • Jonathan Natanael Department of Civil Engineering, Faculty of Smart Technology, Krida Wacana Christian University, Indonesia Author
  • Hans Dermawan Department of Civil Engineering, Faculty of Smart Technology, Krida Wacana Christian University, Indonesia Author
  • Fenny Septiastuti Department of Civil Engineering, Faculty of Smart Technology, Krida Wacana Christian University, Indonesia Author

DOI:

https://doi.org/10.70716/reswara.v4i3.557

Keywords:

Construction Delay, Foundation Works, Risk Factors, Project Time Performance, Structural Equation Modeling

Abstract

Delays in construction projects continue to be a significant problem in infrastructure development, especially in foundation works where field uncertainties are common. This study aims to identify the dominant delay risk factors and examine their influence on project time performance. A quantitative approach was applied using questionnaires distributed to construction professionals, and the collected data were analyzed using Partial Least Squares Structural Equation Modeling (PLS-SEM) and Multi-Group Analysis (MGA). The results indicate that equipment and productivity factors as well as financial and administrative factors have significant effects on project time performance, while other factors were not statistically significant. The structural model showed moderate explanatory power with an R² value of 0.471. The findings also revealed a discrepancy between perceived importance and actual impact, where technical factors were perceived as highly important but operational and financial factors showed stronger direct effects on project execution. In addition, no significant differences were found between contractors and consultants. It was concluded that mitigation strategies should prioritize operational and financial aspects to effectively reduce delays in foundation works.

References

Ahmed, M., & Xu, W. (2023). Investigation of pile construction and productivity loss: An analysis of macro impact factor. World Journal of Engineering and Technology, 11(4), 932–964. https://doi.org/10.4236/wjet.2023.114062

Aldammak, M. M., Hamzah, N. B., & Khoiry, M. A. (2025). Pilot study on delay factors and solutions strategies in government buildings projects in Kuwait: Stakeholders’ perspectives using confirmatory factor analysis (CFA). Buildings, 15(14), 2420. https://doi.org/10.3390/buildings15142420

Alsanabani, N. M., Al-Gahtani, K. S., Almohsen, A. S., & Alsharef, A. (2023). Risk interdependency network model for the cost and time of pile installation in Saudi Arabia using partial least squares structural equation modeling. Applied Sciences, 13(19). https://doi.org/10.3390/app131910886

Alshammari, A., & Ghazali, F. E. M. (2024). A comprehensive review of the factors and strategies to mitigate construction projects delays in Saudi Arabia. The Open Construction & Building Technology Journal, 18(1). https://doi.org/10.2174/0118748368318470240806113627

Assaf, M., Hussein, M., Alsulami, B. T., & Zayed, T. (2022). A mixed review of cash flow modeling: Potential of blockchain for modular construction. Buildings, 12(12). https://doi.org/10.3390/buildings12122054

Chandra, S. S., Sepasgozar, S. M. E., Kumar, V. R. P., Singh, A. K., Krishnaraj, L., & Awuzie, B. O. (2023). Assessing factors affecting construction equipment productivity using structural equation modeling. Buildings, 13(2). https://doi.org/10.3390/buildings13020502

Cohen, J. (1992). A power primer. Psychological Bulletin, 112(1), 155–159. https://doi.org/10.1037/0033-2909.112.1.155

Fashina, A. A., Omar, M. A., Sheikh, A. A., & Fakunle, F. F. (2021). Exploring the significant factors that influence delays in construction projects in Hargeisa. Heliyon, 7(4). https://doi.org/10.1016/j.heliyon.2021.e06826

Gandi, A., Yusuf Tululi, M., & Usman Sumaga, A. (2025). Evaluation of costs and time for the implementation of bore pile foundation work for the BPK RI apartment project in Gorontalo City. Research Review Jurnal Ilmiah Multidisiplin, 3(2), 289–298.

Hair, J. F., Hult, T. M., Ringle, C., Sarstedt, M., Danks, N. P., & Ray, S. (2021). Partial least squares structural equation modeling (PLS-SEM) using R: A workbook. Springer. https://doi.org/10.1007/978-3-030-80519-7

Hassan, A., & Riaz, A. (2024). Analysis of skilled labor shortage in the construction industry of developing countries. Building Engineering, 3(1), 1–12. https://doi.org/10.59400/be2054

Henindia, R., & Suroso, A. (2022). Analysis of the factors causing delay in pile foundation work for medium-story building project. Journal of Applied Science, Engineering, Technology, and Education, 4(1), 27–38. https://doi.org/10.35877/454RI.asci850

Henseler, J., Ringle, C. M., & Sarstedt, M. (2016). Testing measurement invariance of composites using partial least squares. International Marketing Review, 33(3), 405–431. https://doi.org/10.1108/IMR-09-2014-0304

Irankunda, G., Zhang, W., Abdullahi, U. I., Fernand, M., David, B., & Jean-Petit, S. (2025). Understanding critical delay causative factors and their mitigation measures in Burundi communal construction projects: A factor analysis and structural equation modeling approach. Buildings, 15(3), 473. https://doi.org/10.3390/buildings15030473

Jhantasana, C. (2023). Should a rule of thumb be used to calculate PLS-SEM sample size. Asia Social Issues, 16, 1–23.

Khatib, B., Poh, Y. S., & El-Shafie, A. (2020). Delay factors management and ranking for reconstruction and rehabilitation projects based on the relative importance index (RII). Sustainability, 12(15). https://doi.org/10.3390/su12156171

Kuo, C. P., & Vo, D. H. (2025). Causes of delays occurring in linear projects: A survey of prestressed concrete sheet pile retaining wall constructions in Taiwan. Slovak Journal of Civil Engineering, 33(2), 11–25. https://doi.org/10.2478/sjce-2025-0008

Likert, R. (1932). A technique for the measurement of attitudes. Columbia University Press.

Liu, Y., Ng, Y. C. H., Zhang, Y., Yang, P., & Ku, T. (2023). Incorporating geotechnical and geophysical investigations for underground obstruction detection: A case study. Underground Space, 11, 116–129. https://doi.org/10.1016/j.undsp.2022.12.003

Mahirah Sharuddin, N., Azrai Azman, M., Abdul Samad, Z., & Mohd Rodzi, R. (2024). Relationship between schedule delay factors and project performance in civil engineering works. Built Environment Journal, 21, 23–36. https://doi.org/10.24191/bej.v21iSpecial

Mohdar, W., Serang, R., & Titaley, H. D. (2024). Analysis of factors causing work delays bore pile on the school construction project using fault tree analysis (FTA) methods. PARAMETER: Jurnal Matematika, Statistika, Dan Terapannya, 3(1), 19–32.

Rachmawati, F., Ramadhani, H. D., & Nurhidayah, A. S. (2023). Project delay risk assessment. IPTEK The Journal for Technology and Science, 34(1), 60–71. https://doi.org/10.12962/j20882033.v34i1.16263

Rashid, Y. (2020). Analysis of delay factors and their effects on construction projects. Management Science Letters, 10(6), 1197–1204. https://doi.org/10.5267/j.msl.2019.11.039

Rauzana, A., Zahrah, A., & Dharma, W. (2022). Critical delay factors for construction projects in Central Aceh District, Indonesia. F1000Research, 11, 474. https://doi.org/10.12688/f1000research.110024.1

Sullivan, G. M., & Artino, A. R. (2013). Analyzing and interpreting data from Likert-type scales. Journal of Graduate Medical Education, 5(4), 541–542. https://doi.org/10.4300/JGME-5-4-18

Sungkana, S. R. K., Ratnaningsih, A., & Soetjipto, J. W. (2023). Analisis faktor penyebab keterlambatan pelaksanaan pondasi bore pile menggunakan metode fault tree analysis. Bulletin of Civil Engineering, 3(1), 25–30. https://doi.org/10.18196/bce.v3i1.17491

Tariq, J., & Gardezi, S. S. (2023). Study the delays and conflicts for construction projects and their mutual relationship: A review. Ain Shams Engineering Journal, 14(1). https://doi.org/10.1016/j.asej.2022.101815

Yin, H., Khoo, T. J., Liu, Q., & Li, Y. (2025). Factors influencing schedule management delays on residential projects in China: A case study of Yun Yue Dong Fang Project. Turkish Journal of Civil Engineering, 1–25. https://doi.org/10.18400/tjce.1571706

Downloads

Published

2026-06-29

How to Cite

Natanael, J., Dermawan, . H. ., & Septiastuti, F. . (2026). Delay Risk Factors in Foundation Works Using SEM and Multi-Group Analysis. RESWARA: Jurnal Riset Ilmu Teknik, 4(3), 154-170. https://doi.org/10.70716/reswara.v4i3.557